Smoother future in store for bumpy Chase Road in Jackson Township

Dallas Post · February 14, 2017

JACKSON TWP. — A pothole-riddled section of Chase Road that jarred drivers’ nerves for years is on a path towards a smoother future, according to Luzerne County Engineer Lawrence Plesh.

The deteriorating condition of nearly a mile span of Chase Road between Hillside and Huntsville roads has a mix of potholes and road surface patches, giving motorists a bumpy ride.

Residents and Jackson Township supervisors notified Luzerne County about the declining condition of the road.

Plesh, along with the Pennsylvania Department of Transportation, will move forward with a plan to repair the rocky road starting this spring.

In April, the first of two phases to repair the county-owned road will begin, Plesh said.

Fehlinger Construction Group crews will replace two culverts that run under the stretch of Chase Road, Plesh said.

“We issued Fehlinger the notice to proceed,” he said.

The $534,646 project consists of installing one culvert to accommodate Brown Creek and the second to channel stormwater, he said.

Plesh said the precast concrete box culverts are rated as “top of the line load bearing culverts.”

“The culverts will arrive on flatbed trucks on the day the construction crew is ready to install them,” he said.

Culvert replacement is expected to wrap up in May, weather depending, Plesh said.

Road detours will be established during this time, he said.

The start of phase two, which includes road repairs and resurfacing, depends on the completion of right-of-way agreements with some residents.

The easements are required in some areas along Chase Road for swale reconstruction, according to information presented to the Luzerne County Council last week.

Plesh said letters from Keystone Acquisition Service were sent to affected landowners to start the easement negotiation process.

“This process takes time,” he said.

If the right-of-way agreements are settled by May, PennDOT will do a final project review and then advertise for project bids, Plesh said.

The resurfacing project involves, road base repairs, fixing stormwater cross pipes and milling the road surface down nearly two inches in some areas could start as early as this fall or in spring 2018, Plesh said.

Web1 Chase Road 2 1

Chase Road in Jackson Township will receive TLC this year as two culvert replacement projects are planned for this spring and road resurfacing could begin as early as this fall.
/wp-content/uploads/2017/02/web1_Chase-Road-2-1.jpgChase Road in Jackson Township will receive TLC this year as two culvert replacement projects are planned for this spring and road resurfacing could begin as early as this fall. Eileen Godin | Dallas Post
Web1 Chase Road 1 1

The deteriorating condition of Chase Road in Jackson Township has rattled motorists and supervisors for years.
/wp-content/uploads/2017/02/web1_Chase-Road-1-1.jpgThe deteriorating condition of Chase Road in Jackson Township has rattled motorists and supervisors for years. Eileen Godin | Dallas Post

By Eileen Godin